Template for the Integrated Program Plan (revised
4/99)
This template provides guidance for preparing the Integrated Program Plan (IPP). It supplements information found in Appendix B of the FAA Acquisition Management System (AMS). Text of the template that is italicized is intended to guide preparation of the IPP. Non-italicized text defines the format and structure of the document (title page, table of contents, section head and numbers, tables and titles). Not all sections of the IPP template apply to every acquisition program, particularly requirements that will be satisfied by human resource services. Simply state "not applicable" for those sections which do not apply.
INTEGRATED PROGRAM PLAN
(Program Name)
Version: April 1999
Approved
by: Signature
Date: (Co-lead, Integrated Management Team or equivalent Director, sponsoring organization)
Approved
by: Signature
Date: (Co-lead, Integrated Management Team or equivalent Director, providing organization)
Submitted
by: Signature
Date: (Appropriate preparing organization)
| Sponsor Focal Point
|
IPT Focal Point
|
| Name
|
Name
|
| Code
|
Code
|
| Phone Number
|
Phone Number
|
| FAX Number
|
FAX Number
|
Federal Aviation Administration
800 Independence Avenue
Washington, D.C. 20591
Integrated Program Plan
Table of Contents
1 BACKGROUND
- Mission Need..1
- Status...1
2 OVERVIEW
- Program Scope
- Products
3 INTEGTRATED PROGRAM FUNDING
4 INTEGRATED PROGRAM SCHEDULE
5 PERFORMANCE
- Core Work Activities
- Program Management Work Activities
- Procurement Work Activities.11
6 BENEFITS
7 PHYSICAL INTEGRATION
8 FUNCTIONAL INTEGRATION
9 HUMAN INTEGRATION (Revised 4/99)
10 SECURITY
11 IN-SERVICE SUPPORT
12 TEST AND EVALUATION
13 IMPLEMENTATION AND TRANSITION
14 QUALITY ASSURANCE
15 CONFIGURATION MANAGEMENT
16 IN-SERVICE MANAGEMENT
1 BACKGROUND
1.1 Mission Need. Identify the Mission Need Statement and any other
high-level agency document (e.g., FAA Strategic Plan) supporting this program.
Briefly summarize the mission need this program is intended to satisfy.
1.2 Status. State whether this is the initial Integrated Program Plan or a
revision. If this is a revision, briefly explain how the program has changed and why
approval is sought. Cite any top-level management direction since the last approval that
influences this revision. Only major changes to the Integrated Program Plan as a result
of changes to the Acquisition Program Baseline or management direction are approved by the
Integrated Management Team.
2 OVERVIEW
2.1 Program Scope. Briefly summarize this acquisition program and the major
functions or capabilities it is intended to provide. Describe how it relates to the
overall NAS architecture and other interfacing systems or products. Identify and describe
all key elements of this program (e.g., procurement of systems or equipment, modification
or construction of facilities, changes in the physical infrastructure, development of
functional interfaces, procurement of installation or support services).
2.2 Deliverables. List the primary deliverables of this program.
3 INTEGRATED PROGRAM FUNDING
Use the format of Table 1 to show program funding distribution by fiscal year, cost
breakout element, and appropriation in thenyear dollars. Use the same cost
breakout elements and be consistent with the Acquisition Program Baseline and Acquisition
Strategy Paper. If this is a jointly funded program, show other government agency funding.
The following cost elements and cost factors are representative of what may need to be
funded and implemented by the acquisition program:
Table1. Program Funding
Change (#)
(Then-year $M)
|
Cost
Element
|
Appropriation
|
FY
1
|
FY
2
|
FY
3
|
FY
4
|
FY
5
|
FY
6
|
FY
7
|
FY
8
|
FY
9
|
FY
10
|
FY
11
|
FY
12
|
FY
"n"
|
Cost at Completion
|
| Program Management
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Test and Evaluation
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Training
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Data Management
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Physical Integration
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Systems and Equipment
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Implementation
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Product Support
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Operations and Maintenance
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| In-Service Support
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| In-Service Monitor, Assess,
Sustain
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Disposal of Replaced Assets
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Total Program Cost
|
RE&D
F&E
OPS
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The following cost elements and cost factors are representative of what may need to
be funded and implemented by the acquisition program:
| Cost Element
|
Cost Factors
|
| Activities External to Program
|
Remote maintenance monitoring
Rulemaking changes
Activities by other acquisition programs
Airport and local government activities
Regulatory activities
|
| Facilities
|
A&E design
Site-specific design
Construction
|
| Systems/Software
|
Development
Engineering
Production
Reviews and audits
|
| Physical Integration
|
Real estate
Space
Environmental engineering
Energy conservation
Heating, cooling, air-conditioning
Abatement engineering
Civil engineering
Power system
Telecommunications
Hazardous materials
Grounding, bonding, shielding, and lightning protection
Cables
Roads
Sewage
|
| Functional Integration
|
NAS integration
Non-NAS integration
Software integration
Spectrum management
Standardization
|
| Cost Element
|
Cost Factors
|
| Human Integration
|
Human/product interface
Employee health and safety
Special skills and capabilities
|
| Security
|
NAS information security
Physical security
Personnel security
|
| In-Service Support
|
Staffing
Supply support
Support equipment
Technical data
Training and training support
First and second level repair
Packaging, handling, storage, and transportation
|
| Test and Evaluation,
|
Test plans, procedures, reports
Test equipment/tools,
including aircraft
Test staff and training
Test simulators, simulations, modeling
Test articles
Test testbeds and test facilities
|
| IOT&E
|
Test plans, procedures, reports
Test equipment/tools,
including aircraft
Test staff and training
|
| Configuration Management
|
Functional baseline
Product baseline
Physical configuration audit
Functional configuration audit
Configuration change management
Documentation management
|
| Quality Assurance
|
Contractor quality management
Cost/schedule/performance
management
|
| Cost Element
|
Cost Factors
|
| Implementation
|
Planning
Pre-installation checkout
Installation and checkout
Site integration and shakedown
Dual operations
Removal/disposal of replaced assets
|
| In-Service Management
|
Monitoring, assessing, optimizing product performance
Evaluating
capability versus projected demand
|
| Sustainment Engineering
|
Replacing obsolete HW/SW components
Sustaining performance
|
| Program Support Services
|
Program management/technical support
Procurement activities
Special analysis and studies
|
| Operations and Maintenance
|
Operational/maintenance resources required by the IPT for
fielded products
|
4 INTEGRATED PROGRAM SCHEDULE
Develop an integrated program schedule that is a logical networking of the work
activities that will be executed to achieve successful program implementation. Use of an
automated scheduling tool (e.g., MS Project, Primavera, Artemis) is encouraged. Numerically
link the work activities to the narrative description of each in the functional areas
addressed in this Integrated Program Plan Sections 5 through 16. The narrative
descriptions define each work activity, identify the responsible agent, identify any
associated product and approval agent for those products, and define the completion date
for the activity. The integrated program schedule should integrate all activities
(both government and contractor responsibilities) into a single comprehensive plan that
represents the IPTs "road map for program implementation" from the investment
decision through the inservice phase. Show major program milestones and critical
interrelationships between work activities in the integrated program schedule.
The following are representative work activities that could appear in the integrated
program schedule:
| Program Element
|
Event/Milestone
|
| Planning
|
Requirements Document approved
Acquisition Program Baseline
approved
Acquisition Strategy Paper approved
Integrated Program Plan approved
|
| Facilities
|
A&E contract awarded
A&E design complete
Site-specific designs complete
Sites prepared
Construction contract awarded
Beneficial occupancy date
|
| Systems/Software
|
Development SIR released
Development contract awarded
Preliminary Design Review complete
Critical Design Review complete
Full production decision
Production SIR released
Production contract awarded
First article delivery
Production units delivered
|
| Physical Integration
|
Environment studies complete
Civil engineering studies
complete
Abatement activities complete
Site(s) selected
Site(s) procured
Power systems SIR released
Power systems delivery
Telecommunications SIR released
Telecommunications operational
Cable SIR released
Cables delivered
Roads/sewage procured
|
| Program Element
|
Event/Milestone
|
| Functional Integration
|
Interface requirements defined
Interfaces functional
Software interface requirements defined
Software interfaces functional
RMMS/NIMS available
ORD dates of interfacing systems and equipment
Airline equipage actions complete
Actions by regulatory bodies complete
Actions by airport authorities or local governments complete
DOD or other agency agreements finalized
Rulemaking changes complete
Actions by other programs complete
Actions by operations or maintenance organizations complete
|
| Human Integration
|
Human-product interface design complete
Special skills and
training identified
Training courses established
Health and safety issues defined
|
| Security
|
Physical security requirements defined
Physical security
designed
Physical security procured
Physical security fielded
NAS information security defined, designed, acquired, fielded
Personnel security defined, designed, acquired, fielded
|
| In-Service Support
|
Support needs defined, procured, fielded (staffing, supply support,
training and training support, support equipment, first and second level maintenance,
packaging, handling, storage, and transportation, technical data)
|
| Program Element
|
Event/Milestone
|
| Test and Evaluation
|
Operational capability demonstration/test
(may be element of
source selection)
Prototype testing complete
Factory acceptance testing complete
Operational testing complete
Facility/equipment integration testing complete
IOT&E Readiness
Declaration
Site acceptance
testing complete
Field
familiarization testing complete
|
| Independent Operational Test and Evaluation
|
Test
plans, procedures complete
IOT&E
complete
IOT&E report
delivered
|
Implementation and Transition
|
Pre-installation checkout complete
Installation and
checkout complete
Joint acceptance
inspection complete
In-service
decision
Initial operational
capability
Full operational
capability
First Operational
Readiness Date
First
commissioning
Last Operational
Readiness Date
Last
commissioning
|
| Configuration Management
|
Functional baseline defined
Functional
configuration audit complete
Physical
configuration audit
Product baseline
defined
|
| Quality
Assurance
|
QRO on
site
CSSR delivery
|
| In-Service Management
|
Product
monitoring capability in place
Product evaluation
capability in place
|
5 PERFORMANCE
- Core Work Activities.
Use the format below to define the core work
activities to implement the program strategy defined in Section 5.1 of
the Acquisition Strategy Paper. The work activities defined in this
section relate to the overall program
strategy; for example the engineering and development work activities
associated with a software or hardware developmental program or the
design and construction activities associated with establishing a new
facility. Work activities related to such supporting disciplines as test
and evaluation, quality assurance, and configuration management are
defined in other sections of the Integrated Program Plan. The key is to
think through what needs to be done to achieve the capability specified
in the Acquisition Program Baseline, and to build the work activities
that will achieve that capability. Link all work activities to Section
3, Integrated Program Schedule, and include funding requirements in
Section 4, Integrated Program Funding
Core Work
Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| (short
descriptor of first work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| (short
descriptor of second work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| etc.
|
etc.
|
etc.
|
etc.
|
etc.
|
etc.
|
5.2 Program Management
Work Activities. Use the format below to
define the work activities (both government and contractor) to manage this
acquisition program as defined in Section 5.2 Management Strategy, of the
Acquisition Strategy Paper. Link all work activities in Section 3,
Integrated Program Schedule, and include funding requirements in Section
4, Integrated Program Funding.
Management
Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Expanded
Product Team (e.g., activities to formulate and establish
MOUs/MOAs with other organizations that must take action integral to
this acquisition program, and to obtain representation on the
expanded product team. Reporting activities for members of expanded
product team)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Program
Control (e.g., activities to develop program metrics,
track and report program status against metrics, identify and
implement corrective action for emerging problems)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Contract
Management (e.g., periodic management and technical
reviews, cost/schedule status reporting and reviews, qualification
of contract deliverables, contractor deviation reporting and
corrective action)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Requirements Management (e.g.,
activities to manage and control the Acquisition Program Baseline,
activities to monitor and coordinate sitespecific
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Risk
Management (e.g., activities to monitor and report actual
progress for risk areas relative to planned progress; activities to
assess risk, analyze progress, and take corrective action, as
required)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
5.3 Procurement Work
Activities
Use the format below to
define the work activities that will be executed to implement each
individual procurement planned for this acquisition program. Be consistent
with the approach in Section 5.3, Procurement Strategy, of the Acquisition
Strategy Paper. Work activities must address tasking and funding sent to
other agencies and organizations, as appropriate, as well as efforts
associated with contracting with industry. Addresses all aspects of
procuring needed services and capabilities including identification of
potential sources, source selection, competition, contract type, GFE and
GFI, acceptance criteria, warranties, and data rights. Link all work
activities in Section 3, Integrated Program Schedule, and include
funding requirements in Section 4, Integrated Program Funding
Procurement
Work Activity Chart
|
Activity Title
|
Activity Description
|
Responsible Agent
|
Product
|
Approving Agent
|
Completion Date
|
| Prime Contract(s) (e.g., prepare SOW, release SIR, obtain industry comment, evaluate proposals, conduct negotiations, award contract)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing the work)
|
(output from the work activity)
|
(organization / individual that approves the product)
|
(date when the activity must be finished to avoid schedule slippage)
|
|
|
| Support
Contract(s) (e.g., develop SIR, release SIR, evaluate
proposals, conduct negotiations, award contract)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity
must be finished to avoid schedule slippage)
|
| Tasking
to Other Government Organizations
(e.g., develop MOU, define tasking, transfer
funding)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity
must be finished to avoid schedule slippage)
|
6 BENEFITS
Use the format below to
define the work activities to verify that benefits in the Acquisition
Program Baseline are achieved during in-service operation of the products
and services of this acquisition program. Be consistent with the approach
in Section 6 Benefits, of the Acquisition Strategy Paper. If actions must
be taken by parties outside the direct control of the IPT to achieve
benefits (e.g., equipage by the aviation industry, regulatory action), be
sure to include those work activities as well. Link all work activities in
Section 3, Integrated Program Schedule, and include funding requirements
in Section 4, Integrated Program Funding
Benefits Work
Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| (short
descriptor of first work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| (short
descriptor of second work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| etc.
|
etc.
|
etc.
|
etc.
|
etc.
|
etc.
|
7 PHYSICAL INTEGRATION
Physical integration
concerns the integration of a solution to mission need into the physical
environment. Use the format below to define the work activities to achieve
physical infrastructure requirements in the Acquisition Program Baseline.
Be consistent with the approach in Section 7, Physical Integration, in the
Acquisition Strategy Paper. Link all work activities in Section 3,
Integrated Program Schedule, and include funding requirements in Section
4, Integrated Program Funding.
Physical
Integration Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Real
Estate (e.g., activities to acquire any land or other
real property, as required. Include work activities related to
completing appropriate Environmental Due Diligence Audits. Begin
work activities early in solution implementation since the
acquisition of real estate is often very time-consuming)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Space (e.g., work activities to acquire the space
needed to house systems, auxiliary equipment, and personnel, as
appropriate, including adequate workspace for maintenance and access
to serviceable components)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Environment
(e.g., the work activities to achieve
compliance with any environmental or hazardous materials
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Energy
Conservation (e.g., the work activities to be executed to
achieve compliance with the National Energy Conservation Policy
Act)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Heating, Ventilation, Air-Conditioning (e.g., the
work activities to achieve heating, ventilation, and air-conditioning
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
Grounding, Bonding, Shielding, and Lightning
Protection (e.g., the work activities to achieve
grounding, bonding, shielding, and lightning protection
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Cables (e.g., the work activities to achieve cable,
cable routing, and raisedfloor requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Hazardous
Materials (e.g., the work activities to achieve hazardous
materials requirements
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Power Systems and Commercial Power (e.g., the work
activities to achieve power system and commercial power
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Telecommunications (e.g., the
work activities to achieve telecommunications
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Special Considerations (e.g., the work
activities to achieve unique requirements related to such factors as
fiber optics, water and sewer, and roadway access)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
8 FUNCTIONAL
INTEGRATION
Use the format below to
define the work activities to achieve functional integration with other
systems and equipment, the physical plant housing product(s), and human
operators and maintainers, as appropriate. Link all work activities to
Section 3, Integrated Program Schedule, and include funding requirements
in Section 4, Integrated Program Funding.
Functional
Integration Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Integration with NAS (and non-NAS) Elements
(e.g.,
the actions and activities to achieve interface with other systems,
subsystems, networks, facilities, and organizations, including all
states and modes of operation (primary and back-up). Address remote
maintenance monitoring or operational command and control
requirements)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Software
Integration (e.g., the actions and activities to achieve
the following, as appropriate: procedural and technical interface
requirements; communications, protocols, and standards to ensure
compatibility and inter-operability with other fielded systems;
computer resource support requirements including automated test
equipment, required capabilities for integrated computer resources
support, unique user interface requirements, demonstration needs,
and special software certification)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Spectrum
Management (e.g., the actions and activities to achieve
requirements related to spectrum management including certification
of radio spectrum availability, spectrum compatibility with existing
and future components of the National Airspace System)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Standardization (e.g., the actions
and activities to achieve the use of standard products already in
use in the NAS, and to satisfy any ICAO, ISO, space management or
other standard to ensure ease of training, logistics, workforce
mobility, or compliance with international, national, state, and
local codes and laws)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
9 HUMAN INTEGRATION
Typically, human
integration activities are intended to ensure products are well-designed
and appropriate for the human workforce that will operate, maintain, and
support them. Human factors work activities should be consistent with the
nature, size, and complexity of the product(s) being acquired, and should
achieve the following: product design influenced by the capabilities and
limitations of operators, maintainers, and support personnel;
determination of the required level of human performance necessary to
achieve required product performance; necessary personnel training. Link
all work activities in Section 3, Integrated Program Schedule, and include
funding requirements in Section 4, Integrated Program Funding.
Human
Integration Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Human-Product Interface (e.g., the actions
and activities to achieve or resolve the following, as appropriate:
requirements for manpower factors that impact product design; broad
cognitive, physical, and sensory requirements for operators,
maintainers, and support personnel that contribute to or constrain
performance; requirements for human performance that will achieve
effective humansystem interfaces)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Employee
Safety and Health (e.g., the work activities to achieve compliance with
Occupational Safety and Health Administration requirements or other
safetyrelated requirements; achieve operating environment
requirements related to such factors as light, temperature, noise,
fire protection, stairs, and ladders; and update the Occupant
Emergency Plan when implementation will affect facility egress
routes or fire safety)(Revised 4/99)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Specialized Skills and Capabilities (e.g., the actions
and work activities to achieve: cognitive, physical, sensory, and
performance for operators, maintainers, or support personnel; human
performance thresholds and criteria; and constraints, limitations,
and specialized requirements related to training, staffing levels,
and personnel skills)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
10 SECURITY
Use the format below to
define the work activities to achieve physical security, NAS information
security, and personnel security.
Security Work
Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Physical
Security (e.g., work activities related to the design
and construction of a secure physical plant, as well as procurement
of security equipment or resources)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| NAS
Information Security (e.g., work activities to achieve secure
processing, storage, or transfer of information related to air
traffic control or other sensitive information)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Personnel
Security(e.g., work activities related to achieving
security requirements related to personnel, security clearances,
security training, and access control)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
11 IN-SERVICE SUPPORT
Use the format below to
define the work activities to achieve support requirements for this
acquisition program. Organize lifecycle support work activities into the
elements specified in the table. Link all work activities in Section 3,
Integrated Program Schedule, and include funding requirements in Section
4, Integrated Program Funding.
In-Service
Support Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
Staffing (e.g., work activities to define and
obtain person work-hours required to perform operations,
maintenance, and support actions)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Supply
Support (e.g., work activities to determine, obtain,,
catalog, receive, store, and issue items of supply)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Support Equipment
(e.g., work activities to obtain the tools and
equipment required to install and support the operation and
maintenance of the facility, system, or equipment)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Technical Data (e.g., work
activities to obtain recorded information such as manuals,
specifications, drawings, and operational testing procedures to
operate a product over its intended lifecycle)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Training and Training Support (e.g., work
activities to define and obtain processes, procedures, course
material, and skills necessary to train personnel to install,
operate, and maintain the facility, system, or equipment)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
First and Second Level Repair (e.g., work
activities to define and obtain the resources, processes, and
procedures for on-site and second-level engineering support for both
hardware and software)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
Packaging, Handling,
Storage, and Transportation
(e.g., work activities to acquire the resources
and methods to ensure systems, equipment, and support items are
preserved, packaged, stored, and transported safely)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
12 TEST AND EVALUATION
Use the format below to
define the work activities to implement the test strategies in the
Acquisition Strategy Paper. These activities must verify achievement of
requirements and Critical Operational Issues in the Acquisition Program
Baseline. Testing work activities may include: the creation, validation,
and execution of developmental and operational test plans; test events;
test reports; the development or procurement of specialized test equipment
such as aircraft, simulators, hardware/software test beds, and
computerdriven simulation models; the procurement of test articles
and development of test sites; test data recording and analysis; and the
establishment of manpower and training needed by both contractor and
government personnel for the test program. If the contractor's Master Test
Plan forms the basis for the Developmental System Test, ensure FAA input,
control, and approval of work activities and approval points. For
commercial and nondevelopmental programs, review the applicability of
historical test data or commercial product testing in place of
government-unique testing. For Operational System Test, clearly
distinguish between testing at William J. Hughes FAA Technical Center and
field testing, and be sure to coordinate and schedule test requirements
early.
If the program is
designated for IOT&E, the ATS Test Team will develop the IOT&E
Section of the Integrated Program Plan. For designated programs, the
preparation of the Independent Operational Test and Evaluation Readiness
Declaration (IOT&ERD) should be an IPTtest activity under
Operational System Test. Link all work activities in Section 3, Integrated
Program Schedule, and include funding requirements in Section 4,
Integrated Program Funding. The T&E Section for programs designated
for IOT&E is co-approved by ATQ-1 and the IPT lead.
Test and
Evaluation Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| System
Test (e.g., work activities to define system test
objectives; obtain test plans, resources, tools personnel, sites,
and procedures; conduct tests and report findings. System test may
include developmental, operational, site, first article, and product
testing)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization, individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Independent Operational Test and
Evaluation (e.g., work activities to define IOT&E
test objectives; obtain test plans, resources, tools personnel,
sites, and procedures; conduct tests and report findings)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization, individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Field
Familiarization Testing (e.g., work activities to define Field
Familiarization test objectives; obtain test plans, resources, tools
personnel, sites, and procedures; conduct tests and report
findings)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization, individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
13 IMPLEMENTATION AND TRANSITION
Use the format below to
define work activities to field the products of this acquisition program
and put them into operational use. This typically encompasses
implementation planning, preinstallation checkout, installation and
checkout, site integration, system shakedown, dual operations, and the
removal and disposal of replaced systems, equipment, land, facilities, and
other items. Work activities should minimize disruption to current
functions and services during transition to the new capability. Use the
Inservice Checklist as a guide when identifying actions and
activities that need to be planned and executed. Link all work activities
in Section 3, Integrated Program Schedule, and include funding
requirements in Section 4, Integrated Program Funding
Implementation and Transition Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Implementation Planning
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Pre-Installation Checkout
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Installation and Checkout
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Site
Integration
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Dual
Operations
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Removal/Disposal of Replaced Items
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
14 QUALITY ASSURANCE
Use the format below to
define the work to implement quality assurance controls as specified in
the Acquisition Strategy Paper. Include work activities needed to report,
track, analyze, and correct quality problems emerging from contracted
efforts. Link all work activities in Section 3, Integrated Program
Schedule, and include funding requirements in Section 4, Integrated
Program Funding. Identify in Section 11, InService Support, any
training work activities for implementing quality assurance on this
program.
Quality
Assurance Work Activity Chart
|
Activity Title
|
Activity
Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| Contractor Status Reporting
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| In-Plant
QRO
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Independent Validation and Verification
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| Contractor Software Process Monitoring
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
15 CONFIGURATION
MANAGEMENT
Use the format below to
define work activities to achieve configuration management for hardware,
software, data documentation, interfaces, and tools, as appropriate. This
approach will vary based on the product to be procured (e.g., commercial,
nondevelopmental, or development). Typically, the following configuration
baselines should be established and managed: a functional baseline of
decomposed requirements, an allocated baseline of configuration items, and
a product baseline for production. Software configuration management
should cover source code, sourcecodelevel programming
instructions of programmable firmware devices, test procedures, and test
cases. Identify tools that will be used to accomplish configuration
management. Link all work activities in Section 3, Integrated Program
Schedule, and include funding requirements in Section 4, Integrated
Program Funding
Configuration
Management Work Activity Chart
|
Activity Title
|
Activity Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| (short
descriptor of first work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| (short
descriptor of second work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
| etc.
|
etc.
|
etc.
|
etc.
|
etc.
|
etc.
|
14 IN-SERVICE
MANAGEMENT
Use the format below to
define work activities that will executed during in-service management of
this acquisition program. These work activities will become more
definitive as products near and enter the inservice phase of the
lifecycle. In-service work activities should define how the Integrated
Product Team will monitor and evaluate the performance of fielded products
and services, optimize their efficiency and effectiveness, sustain and
extend their useful lifecycle within constraints of available sustainment
funding, and evaluate the capability of fielded products and services to
satisfy projected demand, as preparation for an investment decision on
service-life extension when a major upgrade in capability is needed. Link
all work activities in Section 3, Integrated Program Schedule, and include
funding requirements in Section 4, Integrated Program Funding
In-Service
Management Work Activity Chart
|
Activity Title
|
Activity Description
|
Responsible
Agent
|
Product
|
Approving Agent
|
Completion
Date
|
| (short
descriptor of first work activity)
|
(short explanation of the work activity)
|
(organization, individual responsible for doing
the work)
|
(output from the work activity)
|
(organization / individual that approves the
product)
|
(date when the activity must be finished to
avoid schedule slippage)
|
|