|
 |
Investment Analysis Team
Readiness Checklist
|
|
Complete? |
Readiness Criteria
(Completed by IAT lead prior to IA kick-off meeting) |
|
|
1. A current, approved, and sufficiently quantified Mission Need
Statement exists.
|
|
|
2. Initial Requirements Document is sufficiently mature to begin the
work of an IAT (including definition of operational concepts).
|
|
|
3. Sponsor, IPT, and Architecture representatives authorized to speak
for their organizations are identified and available.
|
|
|
4. The nature of the decision to be asked of the JRC is known (e.g.,
initial investment decision, rebaselining, service life extension).
|
|
|
5. The time frame by which the JRC must make a decision is known and key
factors impacting that time frame are understood.
|
|
|
6. Initial inquiry about existing assumptions and constraints applicable
to this IA is complete. Definitions of major issues have been addressed.
|
|
|
7. Initial inquiry about existing affordability constraints applicable
to satisfying the Mission Need is complete (e.g., Architecture, Mission Need Statement,
SEOAT).
|
|
|
8. Initial assessment of scope of IA and resources required (people,
money, and time) is complete.
|
|
|
9. Background information, such as previous studies and related
documents, is available.
|
|
|
10. Other federal agencies and their interests are identified
(preliminary).
|
|
|
11. The interest and role of the user in the IA is defined
(preliminary). If the "public" is to participate, the requirements of the
Federal Advisory Committee Act have been accommodated.
|
|
|
12. Initial inquiry about the relationship of the approved need to the
Architecture is complete.
|
|
|
13. The agenda for the IA kick-off is complete.
|